Muri Road Development

AGM 2025 guest speaker – Simon Barber

Simon Barber presenting at the Pukerua Bay residents Association AGM

Responding to requests from the wider Pukerua bay community, here are notes from the guest speaker portion of our latest AGM meeting.

Simon Barber, Pukerua Heights Residential Estate development manager for their current development off Muri Road.

Simon shared some slides of the Muri Road developments noting:

  • Silt retention ponds to collect runoff which will make room for the entrance once finished. 144 sites in 6 stages as the market dictates.
  • All the pine trees will be taken down.
  • Top of stage one – pine trees out, platform for first sites. SNA is fenced off to protect the trees there. Once upper area stabilised the proper access area will be put in.
  • Stage two the  old woolshed and pine trees will be removed.
  • Even though it’s hilly sections are benched out for the houses.
  • When trees come down we grind the stumps and mulch the slash then use the mulch to stabilise the site and allow vegetation to grow through.
  • Area above the site there is 50 hectares of native bush that PCC says has ecological significance. We want to bring development to the edge of it so people can access that block.

Questions from the floor:

(Community questions in bold, Simon’s answers in italic)

Pole relocation – Muri Rd to be closed 22 Oct (or 23 Oct)

We currently have work scheduled on Muri Road on 22/10/2025 with the alternative date 23/10/2025. This will require part of Muri Road to be closed

Site hours:

TTM installation: 9am to 9:30am – Work activity/NSC: 9:30am to 3:30pm – TTM removal: 3:30pm to 4pm

Unattended VMS board to be installed 5 days prior with daily site check**

Works methodology:

• install links
• remove overhead wires on pole replacement
• remove old pole
• install new pole
• reinstate overhead wires
• backfill and reinstatement
• remove links

General info:

  • Pedestrian traffic access & safety is a priority
    • STMS/TC to monitor pedestrians and to assist where required and cyclist
    • Cone bars to be placed on cones to isolate the working space from pedestrians.
  • Access to affected driveway/s will be monitored and assisted by STMS/TC as required.

For all the details check out this PDF supplied by Downer

Muri Road Development: May update

Advice has come from Pukerua Holdings Ltd that a notice board at Muri Rd will shortly be erected by the Civil works contractor, Bryce O’Sullivan Contracting, as the new road entrance starts to open and civil works (drainage, roading etc) get underway.

These works will also include the upgrade of a section of Muri Rd between Sea Vista Drive and just beyond the new subdivision entrance (see below).

All affected residents will shortly be updated via letter of these road widening works.

This work is expected to start in August for a period of approx. 10 weeks.

There will naturally be some disruption for this short period, however, the developers believe this will ultimately lead to a much-improved outcome for all residents.   

Muri Road Upgrade Scope of Works

For those wondering who Pukerua Holdings is have a look at https://www.companyhub.nz/companyDetails.cfm?nzbn=9429050538195, https://oversightsolutions.co.nz/profile/PUKERUA-HOLDINGS-LIMITED or

Muri Road Development: April update

The developer’s earthworks contractor is about to commence clearing works on the roadside of Muri Road, starting from Monday 7th April and lasting 2-3 days. Traffic management will be operating so expect some delays. The location of these works are highlighted in red bordered area.

Following this the Contractor will commence earthworks to join into Muri Road at this location. Estimate this work to start in 2-4 weeks, subject to progress on-site. Progress updates will be provided.

Muri Road Development

Pukerua Bay Holdings Ltd which is undertaking the housing development off Muri Road has been in touch with PKBRA to give an update on the development. This is set out below.

As mentioned, we have now completed the 1st phase of our forestry harvest operation and ready to commence the stage 1 earthworks programme at Muri Rd.

Residents will shortly receive notice via their letterbox of the commencement of works on site from the Contractor, Bryce O’Sullivan Contracting (BOSCO).

The works will include opening the new road entrance for the subdivision at the midpoint between 34 and 50 Muri Road.

One additional lot will be created off the ROW at 34 Muri Road.

See below screenshot of the approximate scope of works, marked in red.

As with our forestry logging operation to date, we will continue to comply with all requirements as set out by Porirua City Council.

Our aim is to always keep any disruption to neighbouring residents to an absolute minimum, where possible.