We currently have work scheduled on Muri Road on 22/10/2025 with the alternative date 23/10/2025. This will require part of Muri Road to be closed
Site hours:
TTM installation: 9am to 9:30am – Work activity/NSC: 9:30am to 3:30pm – TTM removal: 3:30pm to 4pm
Unattended VMS board to be installed 5 days prior with daily site check**
Works methodology:
• install links
• remove overhead wires on pole replacement
• remove old pole
• install new pole
• reinstate overhead wires
• backfill and reinstatement
• remove links

General info:
- Pedestrian traffic access & safety is a priority
- STMS/TC to monitor pedestrians and to assist where required and cyclist
- Cone bars to be placed on cones to isolate the working space from pedestrians.
- Access to affected driveway/s will be monitored and assisted by STMS/TC as required.